Krasnoyarsk Krai Boosts Preferential Grid Connection Volumes

In 2025, the pace of contract execution for grid connections in Krasnoyarsk Krai has changed, with energy companies completing over 6,000 agreements.
Mar 1, 2026
0
Accumulated obligations are planned to be fulfilled in stages by the energy company.
Source:
Rosseti Sibir
In Krasnoyarsk Krai, the results for the technological connection of consumers in 2025 have been summarized. Energy companies executed over six thousand contracts for connection to electrical grids, including for preferential categories of applicants.
The main volume of connections fell in the second half of the year, as reported by the branch «Rosseti Sibir» — «Krasnoyarskenergo». If in the first half about 2000 contracts were executed, then in December alone this figure was about 1500. A significant part of the work was done for socially important facilities: outpatient clinics, polyclinics, schools, kindergartens, and communication facilities in remote areas of the krai.
To increase the pace, last year a regulatory agreement was concluded between the grid organization and the government of Krasnoyarsk Krai. Energy companies plan to continue systematically liquidating accumulated obligations. Planned connections will be carried out in stages.
As reported by the Minister of Industry and Trade of Krasnoyarsk Krai, Maxim Yermakov, the authorities control the connection to grids for the preferential category of applicants and ensure that obligations are met on time.
The high pace achieved at the end of the year is the result of systematic work, and we hope that the positive trend will continue, including thanks to the current regulatory agreement, concluded the minister.