Boiler failure at TEC-5 affects Omsk heating

Omsk residents have been warned of a temporary reduction in heating parameters due to a boiler malfunction at the city's largest thermal power plant, TEC-5.
Feb 4, 2026
0

Station personnel have been switched to a 24/7 work schedule.

Source:

Evgeny Sofiychuk / NGS55.RU

The press service of AO TGK-11 reported a disruption in the technological process on one of the boiler units at the city«s largest thermal power plant, TEC-5. This has led to a warning for Omsk residents about a temporary reduction in heating network parameters.

«Due to the disruption in the technological process on one of the boiler units, a temporary reduction in heating network parameters is possible. To maintain the required temperature during severe cold, a backup water-heating boiler unit has been activated at TEC-5,» clarified AO TGK-11.

Due to the accident at the station, TEC-5 personnel have been switched to a 24/7 work schedule.

Omsk residents experiencing issues with heat supply are advised to contact the city«s Unified Duty Dispatch Service at 78-78-78.

Earlier, we reported that Omsk residents from various city districts have been reporting heating problems.