Heat Restored to Vasilyevsky Island Reclaimed Homes
Replacement of the damaged section of the heating main on Nakhimov Street in St. Petersburg was completed ahead of schedule. Residents are having their heating and hot water supply restored.
Mar 11, 2026 0
Emergency work on the one-meter diameter heating main at 20 Nakhimov Street in the Vasileostrovsky District of St. Petersburg was completed on February 1.
As reported by JSC Teploset St. Petersburg, the repair was finished five hours ahead of schedule.
«The problematic section has been replaced, and the network has been filled with coolant. The hydraulic parameters on the section of the heating main for full supply of hot water and heating have been fully restored,» the company stated.
Now, managing organizations need to check the in-house systems to ensure that heat is reaching the apartments.
Recall that on the morning of January 31, radiators stopped working in residential buildings on the reclaimed territories of Vasilyevsky Island. The cause of the shutdown was scheduled repair work on the main pipeline.